Leave a 1/8-inch gap at every edge and end of plywood and OSB sheathing. That’s APA’s recommended spacing for floors, walls and roofs, and the panel maker’s instructions override it if they say something different. Plywood underlayment is the exception: it gets a much smaller 1/32-inch gap.
Quick answer
- Sheathing gap: 1/8 inch at all edges and ends
- Underlayment gap: 1/32 inch
- Where 1/8 inch applies: subfloor, wall sheathing, roof sheathing, T1-11 and other panel siding
- Tongue-and-groove panels: follow the maker’s instructions; some T&G panels space themselves
- Fastest spacer: a 10d box nail, or panel edge clips on roofs
Plywood Expansion Gap Chart
| Application | Gap at edges and ends | How to hold the gap | Notes |
|---|---|---|---|
| Structural plywood sheathing | 1/8 inch | 10d box nail | Floors, walls and roofs |
| Subfloor (square edge) | 1/8 inch | 10d box nail | Joints land on framing or blocking |
| Subfloor (T&G Sturd-I-Floor) | 1/8 inch, unless the panel self-spaces | Follow the maker’s instructions | Some T&G panels space themselves automatically |
| Wall sheathing | 1/8 inch | 10d box nail | Same gap for horizontal or vertical panels |
| Roof sheathing | 1/8 inch | Panel edge clips (H-clips) or nail | Clips also support unsupported edges |
| T1-11 / panel siding | 1/8 inch | 10d box nail | Check the siding maker’s instructions too |
| Plywood underlayment | 1/32 inch | Per APA Form R340 | Much tighter than sheathing |
| Cabinets and furniture | No gap needed | — | Plywood barely moves across its face |
| Very large floors or roofs (80 ft+) | 1/8 inch plus extra expansion joints | Designer sets the spacing | Over long runs the gaps add up |
Warning: Installing panels without adequate spacing increases the risk of buckling when moisture levels rise.
Why Plywood Needs an Expansion Gap
Plywood soaks up and gives off moisture with the weather. When that happens it gets slightly bigger or smaller. The cross-layered veneers keep the change small, but a full sheet still moves.
Although plywood is more dimensionally stable than solid lumber, moisture-related expansion across multiple panels can create enough pressure to cause buckling. APA recommends leaving a 1/8-inch installation gap to accommodate this movement.
If you butt the sheets tight, there’s nowhere for that growth to go. The panels push against each other and bow up between the joists, studs or rafters. That’s called buckling.
What buckling costs you: buckling is generally a looks and serviceability problem, but severe bowing, long exposure to moisture or damaged fasteners may need a closer inspection. You’ll see it as ridges under thin flooring, waves in the shingles, and siding that won’t lie flat. Fixing it after the finish is on is a lot more work than leaving a gap during install.
How to Leave a 1/8-Inch Gap Without Measuring
Use a 10d box nail as a spacer. Tack it at the edge of the panel you just set, slide the next panel against it, then pull the nail. APA suggests this exact trick.
Use panel edge clips on roofs. H-clips hold the gap automatically, and they support the panel edges between rafters. Check whether your local code requires them for your panel thickness and rafter spacing.
Look for “Sized for Spacing” on the stamp. Many sheathing panels are made slightly under 4×8 so that a gap still lets the joints land on standard 16- or 24-inch layout. If you’re not sure what the marks mean, our plywood grade stamp guide walks through each one.
Don’t trim panels to make room. If your sheets are full size and the gaps are pushing joints off the framing, check the stamp and the layout first. The joint still has to land on framing with enough bearing for the nails.
Floors, Walls and Roofs: What Changes
Subfloors

APA generally recommends 1/8-inch spacing at installation, including tongue-and-groove joints. However, some T&G panels are designed to space themselves automatically. Follow the manufacturer’s installation instructions. For the right panel thickness, see our subfloor thickness guide. Over a slab, follow the steps in our guide to installing plywood flooring over concrete, and get the moisture under control first.
Underlayment
Plywood underlayment over a subfloor doesn’t use the sheathing gap. APA recommends leaving a 1/32-inch gap at underlayment edges and ends. A 1/8-inch gap here can show through thin vinyl or sheet flooring.
Walls

Wall sheathing gets 1/8 inch at every edge and end, whether you run the sheets horizontally or vertically. For panel siding like T1-11, use the same gap unless the siding maker says otherwise. Our T1-11 install guide covers the nailing and flashing details.
Roofs

Roof decks take the most weather before the roofing goes on, so this is where gaps matter most. Use 1/8 inch at edges and ends, with clips or a nail as the spacer. For thickness by rafter spacing, see best plywood thickness for roofing, and check panel span ratings on our plywood span chart.
Plywood Expansion Gaps Around Perimeter Walls

APA’s 1/8-inch rule is for the joints between panels. It doesn’t give a separate gap for where a panel meets a wall. In standard framing, the subfloor goes down first and the walls are built on top of it, so there’s no wall edge to gap against.
A perimeter gap comes into play when plywood goes down inside walls that are already built. That happens with plywood over a concrete basement slab, a plywood floor added to a finished room, or underlayment laid wall to wall. In those cases, the gap size comes from the flooring or subfloor system maker, so check their instructions before the first sheet goes down. Never run a panel tight against a concrete foundation wall. Concrete holds moisture, and a panel pressed against it has nowhere to grow. Baseboard and shoe molding cover the gap, so leaving it costs you nothing in looks.
When You Need More Than 1/8 Inch
- Wet climates or panels that will get rained on. APA says bigger gaps may be needed when severe moisture is expected.
- Panels bigger than 4×8. The 1/8-inch rule is based on standard 4×8 sheets.
- Very long buildings. On floors or roofs longer than about 80 feet, all those small swells add up. Large buildings get extra-wide expansion joints at set intervals, and the designer sets where they go.
When You Don’t Need a Gap
Cabinets, shelves, desks and other indoor furniture don’t need expansion gaps between plywood parts. Across its face, plywood moves only a small fraction of what solid wood does. The exception is a solid wood frame, face frame or edging glued to plywood: that wood still moves across its grain, so build it the way you’d build any solid-wood frame.
Should Plywood Expansion Gaps Be Filled or Sealed?
It depends on the panel’s job.
Sheathing (subfloor, walls, roofs): leave the 1/8-inch gaps open. Caulk, foam or wood filler locks the panels together and takes away the room they need to grow. Roofing, house wrap and finish flooring cover the gaps, so they don’t need filling.
Underlayment under thin flooring: this is the one place filling is standard. Under vinyl and other resilient flooring, APA guidance calls for filling the seams and nail holes with a quick-setting filler and sanding smooth once it’s fully cured. That stops the joints from showing through the finish floor. Use a filler the flooring maker approves, since some fillers can discolor vinyl.
Siding: treat vertical joints and flashing the way the siding maker’s instructions say. Don’t invent your own sealing method; a sealed-up joint can trap water behind it.
Products That Make Spacing Easy
This post contains affiliate links. If you buy through them, we may earn a small commission at no extra cost to you.
- Simpson Strong-Tie PSCL panel sheathing clips: the standard H-clip for roof sheathing. Holds the gap and supports the edge between rafters. Buy the size that matches your panel thickness.
- 10d box nails: the cheapest spacer there is. Keep a few in your apron just for gapping.
- Construction adhesive for subfloors: for glued floors. Apply subfloor adhesive to framing and tongue-and-groove joints as directed by the panel and adhesive manufacturers.
How to Check and Correct Existing Plywood Gaps
Check the gaps before anything covers them. Walk every joint on the floor, wall or roof deck. A 10d box nail should slip into a sheathing gap; if it won’t, the joint is tight. On underlayment, look for even, hairline joints of about 1/32 inch.
Don’t panic over a closed gap. Expansion gaps may close naturally as plywood acclimates to its environment. A closed gap does not necessarily indicate incorrect installation or require repair if the panels remain flat and undamaged.
Look for early warning signs. Raised panel edges, ridges you can feel through your shoes, nails backing out and panels that bounce near a joint all point to swelling or fastening problems. Check for moisture too. Panels that are dark, soft or swollen at the edges have been wet. Let them dry before you judge the gaps, because wet panels look tighter than they’ll be once dry.
Fix fastening problems first. Reset popped nails, and add fasteners where the nailing doesn’t meet the schedule. Gaps won’t save a panel that’s loose on the framing.
Get advice before cutting. If panels were installed without gaps, inspect them for buckling and moisture damage before installing the finish. Consult the panel manufacturer or a qualified contractor before cutting relief gaps. Cutting into installed panels can hit nails, framing or T&G joints.
Know when to replace. Delaminated, badly swollen or soft panels should come out. Our guide to wet and warped plywood covers the repair-or-replace call.
5 Mistakes That Cause Buckled Panels
- Butting sheets tight “for a stronger floor.” It isn’t stronger. The first humid stretch can push the panels into ridges you’ll feel under vinyl and see under carpet.
- Ignoring how your T&G panel is supposed to be spaced. Hammering a regular T&G joint fully closed takes away the gap. Forcing an extra gap into a self-spacing panel can leave the tongue too loose. Read the maker’s instructions before the first sheet goes down.
- Letting the deck sit wet with no roof or wrap. Even with good gaps, panels that stay soaked can swell past what the gap can absorb. Get the roofing or house wrap on quickly.
- Using the sheathing gap on underlayment. A 1/8-inch gap is right for sheathing but too wide for underlayment, and it can show through the finish floor. Underlayment gets 1/32 inch.
- Filling sheathing gaps with caulk or filler. That locks the panels together and takes away the room they were left to grow into.
FAQ
How much gap should be between plywood sheets?
1/8 inch at all edges and ends for plywood and OSB sheathing, unless the panel maker says otherwise. Plywood underlayment gets 1/32 inch.
Do tongue-and-groove subfloor panels need a gap?
APA generally recommends 1/8 inch, including at T&G joints. Some T&G panels are designed to space themselves automatically, though, so follow the maker’s installation instructions.
Is the 1/8-inch gap required by code?
APA calls it a recommendation, not a requirement. Some panel makers do require it, so check the instructions that come with your panels.
What happens if I didn’t leave a gap?
The panels may be fine in dry weather and buckle when it’s humid or wet. If panels were installed without gaps, inspect them for buckling and moisture damage before installing the finish. Consult the panel manufacturer or a qualified contractor before cutting relief gaps.
Do OSB panels need the same gap as plywood?
Yes. APA’s 1/8-inch recommendation covers both plywood and OSB structural panels.
Do plywood cabinets need expansion gaps?
No. Plywood moves very little across its face indoors. Only solid wood parts glued to it need room to move.
Bottom Line
Leave 1/8 inch at every edge and end of plywood and OSB sheathing, 1/32 inch for underlayment, and follow the panel maker’s instructions on T&G panels. Use a 10d box nail or panel clips so you don’t have to measure, and leave more when panels are big, conditions are wet or the building is long. Panel buckling is generally a serviceability concern, but severe deformation, prolonged moisture exposure or damaged fasteners may require further inspection. The gap costs nothing and is the easiest way to lower the risk of a wavy floor or roof.